top of page

Here is a blow by blow account of the process we went through in order to build the hydropower station.

We include it to encourage others who may want to do the same and want to know what could be involved.

It took about 6 years from start to finish, but was well worth the effort!

​

wide angle equipment.jpg

2008 – Greenfield & Grasscroft  Residents Association started to think about generating renewable energy in Saddleworth harnessing water power.

  •  Showing of  the film ‘An Inconvenient Truth’ in Delph. Discussion after the film sparked wider interest.

  • A series of meetings of local enthusiasts,  later called the steering group, explored options of an Archimedean screw on the river Tame.

  • This proved unlikely to be viable as there is no weir of sufficient height.

2010 –

  • The option of a turbine on the compensation flow from Dove Stone reservoir was researched. This is an existing legal requirement that United Utilities ensures that a constant flow of water is released into the river to supply industry downstream.

  • United Utilities agreed to a community turbine on the reservoir outflow.

  • A £243,000 EU grant under the Rural Carbon Challenge fund was offered; subject to raising further funding ourselves.

 

2011 – The grant was reviewed under government austerity measures.

 

Summer 2011- The grant was reoffered reduced by only 8%

 

December 2011 –Share offer Launch

 

April 2012 – Share offer closed having raised almost £150,000.

 

June 2012 –

  • H2ope left the project. This was because they felt they lacked sufficient expertise in high head turbines required at Dove Stone.

Summer 2012 –

  • We urgently needed to find a new contract partner. This proved to be a lengthy process as we had to get tenders from several potential partners within EU contract law.

 

October 2012 -

  • In October we selected Renewables First as our new partners.

  • We made preliminary enquires with the Environment Agency about an abstraction licence.

  • A new feasibility report produced by Renewables First showed us a better way to intercept the compensation flow giving us access to the full pressure of the reservoir water. This would almost double the power output with a similar rise in our potential revenue generation.

 

November 2012-

  • We had our first formal meeting with United Utilities to discuss the siting of the turbine. Renewables First's initial proposal was to house the turbine in a structure over the existing reservoir. United Utilities and the directors rejected this solution because of turbulence in the basin at time of severe overflow. United Utilities suggested we investigate a possible site inside the reservoir pump house.

 

December  2012 –

  • An investigation of the pump house was started.

 

February 2013 –

  • The pump house was finally rejected because of limited space and restricted access arrangements.

  • A new site was found for the turbine in a small building in front and to the right of the pump house.

 

March 2013 -

  • Technical agreement was obtained with United Utilities for this new site.

April 2013 -

  • A ‘heads of agreement’ with United Utilities was put in hand. A legal agreement is needed before ordering a turbine, which is a major capital spend.

  • Local Authority planning approval sought.

  • An abstraction licence will probably not have been required from the Environment Agency, but we expected them to rule on whether any provision for protection of fish is required.

May 2013 

  • A meeting was held with United Utilities on 3 May to sign off of the technical design and  ‘heads of agreement’ prior to ordering the turbine. The turbine was ordered. Ecowave, a British supplier was used.

June 2013 

  • United Utilities specified we must appoint a panel engineer to confirm safety of our plans before final approval could be given.

July 2013 

August 2013

  •  Heads of agreement with UU  agreed. This covers the need for a decommissioning bond. Drafting of full lease put into train. Bridging finances put in hand with Key Fund.

December 2013 

  • The chamber for the turbine is below ground level and also the water table, so the building is lined with a waterproof membrane.

  • Construction started with excavation of the turbine chamber and of the sump, for water to run into after passing through the turbine. 

  • The chamber for the turbine is below ground level and also the water table, so the building is lined with a waterproof membrane.

  • February 2014 

  •  The output connection was made to the stilling pool and thus to the river .

  • March 2014

  • The pipework connections were engineered to divert the existing outflow of water through the turbine house.

  • The turbine was installed.

  • Costs had escalated, so a second share offer was made raising a further £80,000.  This resulted in the capital invested by shareholders matching the grant from DEFRA.

  • April 2014

  •  

  •  The cross piece was put in place. Fortunately there had been quite a lot of rain so that the overflow from the reservoir more than made up for the loss of compensation water during the connection process.

May 2014

The transformer was installed for the connection to the National Grid.

All external work was completed and commissioning started.

​

June -August 2014

  • A phone line was installed and a broadband connection was made to facilitate remote control and monitoring + email reception of warnings of problems.

  • Team of volunteers trained to deal with the everyday running.

  • Commissioning and testing of the system to ensure no loss of compensation water to United Utilities.

  • United Utilities want the flow of compensation water to be above the legal minimum so output is 43KW: 10% more than originally expected.

  • Turbine started up for normal production.

​​

September 2014

  • Official public switch-on by Adrian Ramsay, Chief Executive of The Centre for Alternative Technology, Machynlleth.

​

Adrian Ramsay, the Mayor of Oldham, Cllr Fida Hussain, the Mayoress,

Bill Edwards SCh chairman, and pupils from Friezland School

​

An inconvenient Truth.jpg
RF logo (1).png
2014-01-17 phillida 013.jpg
Break through sump to basin - Jim.jpg
Bespoke pipework - Richard.jpg
Crosspiece in place and pipework towards
Lowering turbine - Bill.jpg
transformer.png
View across site - Bill.jpg
Cutting the ribbon 2.JPG
bottom of page